Safety, Quality, Sustainability and On Schedule
Temporary Curtain Walls - FleX Walls©
University
Princeton, NJ
Project Size: 50 Openings
Project Duration: 1.5 Weeks
Global Wrap® worked with the client on a multi mobilization project involving taking down the Global Wrap temporary opening enclosures from over fifty openings and then reinstalling them after the contractor installed their materials on the side walls of each opening.
Dust Containment Systems
A Food Plant
Morgantown, PA
Project Size: 300’L x 25’H’
Project Duration: 4 Days
We Installed the Global Wrap 12 mil, fire retardant shrink film temporary dust barrier wall, 300’L x 25’H’ to underside of roof deck. Secured to floor deck and underside of roof deck with Hilti nails. Heat shrinked all surfaces.
Shrink Wrap Dome
State capitol building
Project Size: 13,600
Project Duration: 1 Week
Recently We installed our proprietary wrap system over the dome of a state capitol building being restored. The sides of the dome tower were tarped with the conventional grommet tarps. A tornado came through the area tearing the tarps off, however Global Wrap remained tight.